Duluth Schools ISD 709 - Long Range Facilities Plan

Register for Updates!

Enter your email address for regular updates on the Long Range Facilities Plan.

Frequently Asked Questions

Below are answers to the most frequently asked questions about the Long Range Facilities Plan. If you do not see the answer to your question, visit our Ask a Question page to submit your own.

How much of the Facilities Plan is complete?

Two schools opened in September 2008:
Updated Stowe Elementary
Updated Lakewood Elementary

Two schools opened in September 2009:
Updated Lowell Elementary
Updated Homecroft Elementary

Five schools opened in September 2011:
New Lester Park Elementary
New Piedmont Elementary
New Laura MacArthur Elementary
Updated Denfeld HS
Updated East HS

Construction is well underway at two schools, which are scheduled to open in September 2012:
Updated Ordean East Middle School
New Lincoln Park Middle School

Two schools are scheduled to open in September 2013:
Updated Myers-Wilkins (formerly Grant) Elementary
Updated Congdon Park Elementary